Today’s paper

Malaysia · 9 Nov 2026

Sunview adds a RM40.5 million bank line for a battery on the LSS4 Pekan project - the line covers 78.17% of that job, the box size is blank, and the net rise in facilities is RM20.5 million

On 4 November 2026 Sunview said SAM 2 accepted a supplementary letter from Bank Kerjasama Raykat Malaysia, dated 2 October 2026. A new facility part-finances installation of a battery on the LSS4 Pekan project under the corporate renewable energy supply scheme, up to RM40.5 million or 78.17% of that cost, whichever is lower. Total facilities move from RM170 million to RM190.5 million. A performance guarantee in favour of Tenaga Nasional falls from RM45 million to RM25 million. No megawatt-hours, no profit rate and no sen rate are printed.

  1. Markets · 9 Nov 2026

    Pexapark's Spanish model lifts a 2027 solar capture factor from 0.45 to 0.82 when a four-hour battery charges only from the plant - grid charging reaches 0.93, Germany's gray case is worth €112, and no contract price is printed

    On 3 November 2026 Pexapark said a four-hour battery sized at half the solar plant's power, charging only from that plant, lifts Spain's 2027 capture factor from 0.45 to 0.82. The note calls that an 82% uplift worth €45 a megawatt-hour. The same box, also allowed to charge from the grid, reaches 0.93. In Germany the plant-only case is worth €46 and the grid-charging case €112. The curves are September 2026. The note names no site and no signed price.

  2. Australia · 9 Nov 2026

    Frontier signs the Waroona revenue floor and leaves the price off the page - debt is up to A$280 million, the battery is 81.5 MW with no hours on the company pages, and financial close is still ahead

    On 2 November 2026 Frontier Energy said it executed debt facilities of up to A$280 million for Stage One at Waroona, a 132 MW solar plant and an 81.5 MW battery about 120 km south of Perth. Financial close still required a Capacity Investment Scheme agreement and an interest-rate hedge. On 6 November the company said the agreement is signed, the floor price is confidential, and support with Western Australia's reserve capacity scheme runs to 2042. The 6 November page does not say the hedge is done. Neither November page prints megawatt-hours or a cent rate.

  3. Storage · 8 Nov 2026

    Pioneer Cement signs for a 15 MW / 30 MWh battery and 10 MW of solar at Chenki - the rupees are blank, completion is 31 March 2027, and a 3 November letter prints 31 MW with no battery

    On 6 November 2026 Pioneer Cement told the Pakistan Stock Exchange it signed with Pragmatic Engineering Solutions and Sungrow to supply and install a 15 MW / 30 MWh battery and an additional 10 MW of solar at its Chenki plant in Khushab. The letter prints no rupee price. A 3 November letter on the same plant says 28.265 MW of solar is energized and the total is being taken to 31 MW, with sustainable power expected to meet approximately 45 percent of annual requirements. That letter names no battery.

Also filed

  1. Alectra's three Ontario batteries are in service at 80 MW and 320 MWh - the IESO term is 20 years, the budget is blank, and the boxes are not on a workplace meter

    Canada · 8 Nov 2026

  2. Sibenik's 60 MW / 120 MWh battery is open on the old TLM site - HRT prints about €60 million, the company page prints no euros, and the box sells a frequency service to the grid

    Croatia · 8 Nov 2026

  3. AirTrunk's offtake sits on the Mulwala solar farm, now at full output at 31 MW - the 25 MW / 100 MWh battery is still ahead, the term is blank, and a portion of the energy is uncontracted

    Australia · 7 Nov 2026

  4. GridPoint prints a 2 GW on-site battery target across more than 20,000 commercial buildings - the boxes are not in, the extra 15% is the company's line, and the release names no solar

    United States · 7 Nov 2026

  5. Ireland's community grant stops school solar at 2 kWp for a primary and 4 kWp for a secondary - the 4 November answer does not lift the cap, the 50% line is not the business grant, and no battery is named

    Ireland · 7 Nov 2026

  6. Ahold Delhaize takes 370 GWh a year for 10 years from a 1.3 GWp Romanian solar park and a 300 MW wind farm - the price is blank, the shops do not take the power, and the page names no battery

    Markets · 6 Nov 2026

  7. Dubrovnik airport's solar and battery bids are €4.89 million and €8.16 million on a JUGinfo reading of the opening record - both sit above a €4.2 million estimate, the page does not match a firm to a price, and no award is in

    Croatia · 6 Nov 2026

  8. TNB, IOI and 12 smaller firms cap equity at RM606.2 million for 500 MWac of solar and a 250 MW / 1,000 MWh battery at Bahau - the build cost is blank, The Star prints a 21-year DayOne line, and the filing page prints no sen rate

    Malaysia · 6 Nov 2026

  9. Cactos prints 16 MW and just under 65 MWh for OK's Danish station batteries, and OK's October page prints about 30 MW and about 60 MWh - 70 sites, a 520 kWh cabinet, and the box only stores power

    Storage · 5 Nov 2026

  10. Exelon sketches $3 billion to $7 billion for 1.5 GW to 3.5 GW of utility-owned batteries - the New Jersey box is 500 MW and four hours, the call prints no build cost, and a questioner said $2 billion

    United States · 5 Nov 2026

  11. Ontario keeps the workplace solar rates at $1,000 and $770 a kilowatt and moves the size line to 12 kW on 30 November - the regional adder ends the night before, the live page still prints 10 kW, and the update names no battery

    Canada · 5 Nov 2026

  12. Modo puts Western Australia's grid-battery index at $184,100 a megawatt for October - capacity credits are 91% of that revenue, the 2028-29 price on AEMO's page is a different year, and a factory invoice is not in the index

    Markets · 4 Nov 2026

  13. Northern Solar accepts two CRESS letters for 189 MWac of solar, each job coupled with a battery, for data centres in Johor - the ringgit are blank, the battery size is blank, and the letters are not the supply contract

    Malaysia · 4 Nov 2026

  14. Victoria's SEC replaces the Glenrowan solar offtake with a 10-year contract that adds a 102 MW four-hour battery - the price is blank, a July page printed 100 MW and $130 million, and financial close is still ahead

    Australia · 4 Nov 2026

  15. A cooperation page prints a 9,030 kW battery near Koprivnica and a 750 kW box in Zelina - the flexibility fee is blank, and the fair note describes three ways to run the box

    Croatia · 3 Nov 2026

  16. A Holycross dairy farm runs 29.8 kWp of solar and a 45 kWh battery - one autumn day is priced at about €9.92, the system price is blank, and the three-year line is the installer's expectation

    Ireland · 3 Nov 2026

  17. UC San Diego's campus microgrid is the site of an 8 MW / 40 MWh battery loan - the dollars are blank, a February filing prints 8 MW / 32 MWh, and the release names no solar

    United States · 3 Nov 2026

  18. A Bowmanville cement plant is taking a 50 MWh battery with nothing due up front - the megawatts are blank, one trade page hopes for May 2028, and the box charges from the grid

    Canada · 2 Nov 2026

  19. A Steinach timber plant is adding two 197 kWh batteries beside 520.76 kWp of roof solar - the CHF 35,000 is the panels, the 72% is an expectation, and the box only holds leftover noon

    Storage · 2 Nov 2026

  20. Malaysia puts a 30% renewable line on data centres - August use was 1,374 MW against 2,346 MW booked, the test is not one sentence, and the speech names generators where a battery would sit

    Malaysia · 2 Nov 2026

  21. A Pilbara lithium mine takes at least 325 GWh a year for 20 years from Fortescue's solar and battery grid - the cents are blank, the supply is not firm, and the on-site battery stays

    Australia · 1 Nov 2026

  22. A roof under 100 kW can fall under the mid-scale certificate rules if a related system pushes the total over - ten shops on one street meter can stay separate, and a 10 MW job cannot claim the first megawatt in stages

    Australia · 1 Nov 2026

  23. Western Australia opens 3% loans of $300,000 to $15 million for factory solar and batteries - the worksite puts in 20% cash, and spend before the deed is out

    Australia · 1 Nov 2026

  24. A logistics yard in Aichi has taken delivery of a 2,742 kWh battery beside 858 kW of roof solar - operations are scheduled for February 2027, and the yen are blank

    Storage · 31 Oct 2026

  25. Maryland opens a closed auction for grid batteries of at least 20 MWh and four hours - this round is up to $100 million, the bid cap is hidden, and a net-metered roof is off the generation line

    Markets · 31 Oct 2026

  26. Three Ha Tinh factories are taking power from up to 22 MWp of roof solar and a 45 MWh battery - the cost line is nearly 3.5 billion dong a year, and the tariff is blank

    Storage · 31 Oct 2026

  27. Egypt Aluminium takes a 25-year contract for power from 569 MW of solar and a 100 MWh battery - the price is blank, and the smelter does not own the plant

    Storage · 30 Oct 2026

  28. Powertown will fund 125 kW or 250 kW batteries at Brockton workplaces with nothing due up front - a laundry puts the cut at about $30,000 a year, and the savings split is blank

    United States · 30 Oct 2026

  29. Cemex tells a Zagreb fair it uses 145 GWh a year and that 6.4 MW of solar covers 6% - the 18 MW finish was spoken at the fair, and the company page prints a different next step

    Croatia · 29 Oct 2026

  30. CIMB pairs a battery with 20.2 GW of the 24.3 GW of new Peninsular solar on its 2026-2035 sheet - about RM1 million a megawatt for the battery and RM3 million for the panels

    Malaysia · 29 Oct 2026

  31. Ontario caps an inverter plant at 75 MW on a 115 kV line in its next contract round - Belleville's list is 10 MW of solar and a 60 MW battery, and a local factory feeder is off the map

    Canada · 29 Oct 2026

  32. A citrus farm with 22 power accounts is lining up 3 MWp of solar and a 6.6 MWh battery on one private line - the tariff is blank

    Storage · 28 Oct 2026

  33. A Minas Gerais poultry farm is running 378 kWp of solar and a 1.29 MWh battery - the 50% bill cut is an estimate, and the diesel generator stays

    Storage · 28 Oct 2026

  34. LevelTen puts the 25th percentile of German solar-plus-battery offers at €65.50 a megawatt-hour, down 12.7% - Spain's solar-only cut is €30.93, and a posted offer is not a signed contract

    Markets · 28 Oct 2026

  35. Google and Voltus added 1,070 MW of flexible PJM capacity - a workplace battery can join the pool, and the contract prints no payment rate

    United States · 26 Oct 2026

  36. Grid batteries set the NEM spot price in 48% of September-quarter intervals, wholesale power averaged $63, and they beat gas in the evening peak

    Australia · 26 Oct 2026

  37. Irish business power averaged 24.1 euro cents a kilowatt-hour in the first half of 2026, the highest EU average in SEAI's table, and the battery count leaves out the box on site

    Ireland · 26 Oct 2026

  38. A Czech industrial group signed a 20-year contract for power from 27 MW of solar and a 10 MW battery - the developer owns the plant, and the price is blank

    Storage · 21 Oct 2026

  39. Dominion sketches 3.5 GW of grid batteries over 20 years - the April law tells that utility to seek 16,000 MW of shorter batteries and 4,000 MW of longer ones

    United States · 21 Oct 2026

  40. A Malaysian company buying green power across the grid pays 4 sen per kWh - the developer's 14 sen fee is a different line, fixed for 10 years

    Malaysia · 20 Oct 2026

  41. Ontario's draft lets a transmission battery sell energy, reserve and frequency control in the same hour - the pay formula is blank, and a factory feeder is out

    Canada · 20 Oct 2026

  42. A Geelong campus is running a 100 kWh lead-acid battery - the Sydney factory copy is still a plan, 600 mm from the wall

    Australia · 19 Oct 2026

  43. Ireland doubled a workplace loan pot to €1 billion - renewable energy is named, and the extra green discount is 0.25%

    Ireland · 19 Oct 2026

  44. A La Fox factory plans a 5 MWh battery on site - ComEd's storage rebate is $300 or $250 a kilowatt-hour, and this project has not been paid it

    United States · 18 Oct 2026

  45. Grid batteries set the NEM spot price in 36% of intervals in the June quarter, up from 17%, and the discharge price fell to $107

    Markets · 18 Oct 2026

  46. Croatia puts €30 million on the table for farm and food-plant solar and batteries - first in, first paid, from 9 November

    Croatia · 17 Oct 2026

  47. The grid couldn't give a Barcelona factory more power, so it bought a 3.87 MWh battery instead of waiting

    Storage · 17 Oct 2026

  48. A Galway medical-device plant built a 6 MWh battery and 4 MW of generators around its solar - and the installer behind it now sells through Energia

    Ireland · 16 Oct 2026

  49. Honda Malaysia put 5.6 MWp of solar and a 5.8 MWh battery on its factory - and it still covers only about a tenth of the power bill

    Malaysia · 16 Oct 2026

  50. A Woodstock car-parts factory put in a 3.6 MW battery for two hours of peak cut - financed by someone else

    Canada · 15 Oct 2026

  51. US buyers now pay about 20% more for Chinese storage cells before tariffs - freight flipped the map

    Markets · 15 Oct 2026

  52. A Riverwood factory warehouse put in a 200 kWh battery on a 50 kW inverter - four hours of push, and a A$15,000-a-year estimate

    Australia · 14 Oct 2026

  53. A Vermont chip factory added about 6 MW of solar and a 16 MW battery - and the battery is the part that pays

    United States · 14 Oct 2026

  54. Varaždin's technology park put 60 kW of solar on its roof so it would not lift tenants' rent

    Croatia · 14 Oct 2026

  55. A Johor precast concrete factory put 573 kW of solar and a 522 kWh battery on site - about two hours of battery at full push, built in roughly three months

    Malaysia · 13 Oct 2026

  56. France's biggest battery published its first report card - 145 full cycles in 125 days and 70.5 GWh fed back from a 240 MW / 480 MWh site

    Storage · 13 Oct 2026

  57. Alberta's biggest battery is online - Northland's Jurassic box is 80 MW / 160 MWh, two hours at full power, with a 15-year offtake covering all of it

    Canada · 12 Oct 2026

  58. European C&I battery shelves may get crowded into early 2027 - utility-scale prices look steadier

    Markets · 12 Oct 2026

  59. DENSO put 5.25 MWac of solar beside its Athens Tennessee plant - more than 10,000 modules, about 14% of the plant's yearly power, no battery named

    United States · 11 Oct 2026

  60. NSW cleared a 125 MW / 1,000 MWh eight-hour battery near Narrabri - Energy Vault owns it, Enervest delivers, LTESA runs 14 years

    Australia · 11 Oct 2026

  61. Batteries now beat gas peakers on cost in 43 markets. A battery still runs out after four hours.

    Markets · 10 Oct 2026

  62. Germany's latest innovation auction went entirely to solar-plus-storage - 480 MW at an average €0.0514 per kWh

    Markets · 10 Oct 2026

  63. JA put a 125 kW / 261 kWh solar-plus-battery cabinet on European pre-order - one box for panels, storage and 10 ms backup

    Storage · 10 Oct 2026

  64. Buying green power through CRESS just got a cheaper grid fee: 14 sen per kWh, down from 20 - and a RM34m solar build lands 19 days later

    Malaysia · 8 Oct 2026

  65. Four First Nations want to power an Ontario gold mine with an 8.5 MW solar farm - the permit takes longer than the build

    Canada · 8 Oct 2026

  66. Two Long Island batteries are switched off over a 2023 fire - New York regulators point at the fire suppressant, not the batteries

    United States · 8 Oct 2026

  67. Ausgrid will buy the solar a warehouse roof can't use - 16-year contracts, about 8c a kilowatt-hour expected, in two trial areas

    Australia · 7 Oct 2026

  68. Three Spanish factories now run 62.5 MWh of batteries beside 34 MWp of solar - the first three of ten in a 366 MWh job

    Storage · 7 Oct 2026

  69. A landlord with up to 240 offices, warehouses and clinics handed its roofs to an energy company - about 70 MW of solar and 300 MWh of batteries, with no capex for tenants

    Australia · 6 Oct 2026

  70. Ireland's business solar grant nearly doubles from today - 45% of eligible costs for nine months, up from about 23%

    Ireland · 6 Oct 2026

  71. Ireland puts money behind home batteries again from 6 October - and says businesses using the solar support can cut energy costs by up to €300,000 a year

    Ireland · 5 Oct 2026

  72. NSW's Waratah Super Battery hit final commercial ops - 850 MW on an old coal site, built to catch grid shocks in milliseconds

    Australia · 5 Oct 2026

  73. A US tech company booked Malaysian firm solar for its data centres - 680 MW of panels and a four-hour battery, on a twenty-one year term sheet

    Malaysia · 2 Oct 2026

  74. Queensland's wholesale power price fell 40% in a year - the state generator credits the battery build-out

    Australia · 2 Oct 2026

  75. FRV just switched on a 100 MW two-hour battery in southwest Victoria - its first big standalone box in Australia

    Australia · 1 Oct 2026

  76. A Victorian hybrid solar-plus-battery hub just hired its Stage 1 builder - Gamuda takes the Mortlake EPC

    Australia · 30 Sep 2026

  77. Mayo just cleared a revised plan for an 80 MW four-hour battery next to an SSE gas station - FID is still SSE's call

    Ireland · 30 Sep 2026

  78. A Moroccan phosphate mine switched on a five-hour battery next to its solar - lunchtime sun for the night shift on the plant

    Storage · 29 Sep 2026

  79. Spain will put a new capacity charge on power bills - and pay factories that can cut load when the grid is stressed

    Markets · 29 Sep 2026

  80. From Wednesday, a factory roof between 100 kW and 1 MW can use the same small-scale certificate paper as a house

    Australia · 28 Sep 2026

  81. Ireland will stop charging grid batteries like a factory when they fill up - from 1 October they pay the generator fee instead

    Ireland · 28 Sep 2026

  82. Amazon booked a four-hour Victorian battery without building it - Australia's first corporate storage toll outside the energy industry

    Australia · 25 Sep 2026

  83. Croatia's parliament passed power market changes that push business PPAs and strengthen self-producers

    Croatia · 25 Sep 2026

  84. Greece put €8.15 million toward workplace batteries next to solar. Most of the programme budget is still sitting unused.

    Storage · 24 Sep 2026

  85. US commercial solar got 5.6% dearer in a year, to $1.77 a watt, even as module prices fell

    United States · 24 Sep 2026

  86. Victoria's state utility bought into a long battery - and booked half its power for fifteen years for business customers

    Australia · 24 Sep 2026

  87. Arizona's big utility booked a four-hour battery for twenty years - and the banks closed $220 million behind it

    United States · 23 Sep 2026

  88. Croatia signed 47 business battery grants worth EUR 16.3 million, using only about 30% of the money on offer

    Croatia · 23 Sep 2026

  89. Malaysia publishes a fixed grid fee for corporate solar that can deliver for four hours

    Malaysia · 23 Sep 2026

  90. A German steel mill bought solar - and the right to run the batteries when the plant needs power

    Markets · 22 Sep 2026

  91. Google banked leftover solar in batteries so clean power showed up in the hours it actually used

    United States · 22 Sep 2026

  92. Australia switched on its first eight-hour grid battery. It fills up at noon and runs into the night.

    Australia · 21 Sep 2026

  93. Istria switched on its first public-building solar roof, 100 kW on Umag's health centre, with three more on the way

    Croatia · 21 Sep 2026

  94. US workplaces bought batteries in bulk last quarter. The install record was not only utilities.

    United States · 21 Sep 2026

  95. Canberra’s small-scale battery discount stops at 100 kWh. NSW’s workplace voucher goes to 30 MWh.

    Australia · 19 Sep 2026

  96. Ireland’s panel grant is not the payment for leftover noon.

    Ireland · 19 Sep 2026

  97. Malaysia closed new applications on the old one-for-one meter. The 2026 workplace path is ATAP.

    Malaysia · 19 Sep 2026

  98. The Australian battery discount is paid in traded paper. Tuesday’s price is not your contract.

    Markets · 19 Sep 2026

  99. Ireland will help pay for workplace solar panels. The battery is a separate bill.

    Ireland · 18 Sep 2026

  100. NSW will knock money off a workplace battery. The published cut is a range. Your quote is a different number.

    Australia · 18 Sep 2026

  101. Meta added a 144 MW Texas solar farm to its Apex deals, taking the green certificates while the grid gets the power

    United States · 17 Sep 2026

  102. A Croatian oil factory switched on 3.5 MW of solar and a 4.5 MW / 9 MWh battery - self-use first, surplus into the box

    Croatia · 16 Sep 2026

  103. If the lights are still on after sunset, a battery is how lunchtime sun works the night shift.

    Storage · 15 Sep 2026

  104. Malaysia pays a business a bulk rate for leftover lunchtime sun. That is not the rate on your bill.

    Malaysia · 15 Sep 2026

  105. The Malaysian home rebate tops out at RM3,000. It does not pay for a factory roof.

    Malaysia · 15 Sep 2026

  106. The US set final duties on solar cells from India, Indonesia and Laos, up to 249% combined for India

    United States · 14 Sep 2026

  107. US commercial solar installs rose 11% in the second quarter while home solar hit a five-year low

    United States · 10 Sep 2026

  108. Croatian power traded below zero at Sunday lunchtime, while neighbours' evening prices passed EUR 225

    Croatia · 6 Sep 2026

  109. Croatia's first home battery grant filled in about a day: 9,320 applications, 1,460 for batteries

    Croatia · 4 Sep 2026

  110. Illinois approved 600 MW of new four-hour batteries, but the PJM zone got only 80 MW of its 588 MW target

    United States · 3 Sep 2026

  111. A new US order on foreign grid equipment puts battery projects first in line for delays, BloombergNEF says

    United States · 1 Sep 2026

  112. Croatia lets standalone batteries get permits in industrial zones before local plans catch up

    Croatia · 28 Aug 2026

  113. The US widened its block on new foreign-made grid inverters to cover wired connections, with a carve-out for 45X makers

    United States · 24 Aug 2026

  114. New Jersey proposed paying home batteries for grid duty, and says business batteries at critical sites come next

    United States · 19 Aug 2026

  115. Nevada's main utility signed for 25 years of solar with a four-hour battery: 400 MW of panels, 1,600 MWh of storage

    United States · 18 Aug 2026

  116. Tesla filed plans for a $10.1 billion solar factory campus in Texas, with production from 2029

    United States · 12 Aug 2026

  117. Dubrovnik airport plans solar roofs over its car parks and a 3.3 MWh battery, with no power sold to the grid

    Croatia · 11 Aug 2026

  118. Vukovar's water company is building solar with a battery at its wastewater plant and expects over EUR 300,000 a year off power costs

    Croatia · 11 Aug 2026

  119. A 5.3-hour battery is going up next to Ohio's data centre cluster: 200 MW / 1.06 GWh, the biggest on the PJM grid

    United States · 7 Aug 2026

  120. From 4 December, imported solar modules in the US carry a $0.38 per watt price floor plus a 15% tariff

    United States · 7 Aug 2026

  121. Orsted switched on a 250 MW / 500 MWh battery beside a Texas solar farm, and runs it separately from the panels

    United States · 6 Aug 2026

  122. HEP confirmed its Sukosan solar plant comes with a battery of up to 200 MWh, and the estimate rose to EUR 65 million

    Croatia · 5 Aug 2026

  123. Texas paused its data centre hook-up queue: 474 GW of requests, about 90% of them data centres

    United States · 5 Aug 2026

  124. Costco took a Florida distribution centre off the grid with solar and batteries, and nobody said how big the system is

    United States · 28 Jul 2026

  125. Croatia sold 312,171 green power certificates in one day, at about EUR 1.12 to 1.46 each

    Croatia · 28 Jul 2026

  126. PJM wants new data centres that bring no power of their own to cut back first near a grid emergency

    United States · 28 Jul 2026

  127. Tesla signed to buy about 1 TWh a year from an Arizona solar farm with a four-hour battery

    United States · 28 Jul 2026

  128. Croatia's first energy community is live: 17 members share one fire station roof, no battery

    Croatia · 27 Jul 2026

  129. Croatian power traded below zero for 257 hours last year, and the regulator reads it as a case for batteries

    Croatia · 23 Jul 2026

  130. Solar and batteries were 91% of new US power capacity in the first quarter, and California's batteries met 36% of demand at one point in July

    United States · 23 Jul 2026

  131. A Karlovac pasta maker paired a new line with 160 kW of solar and reports over 15% off its power use in the trial

    Croatia · 22 Jul 2026

  132. Croatia's regulator adopted a written list of what blocks companies from using their own solar power

    Croatia · 21 Jul 2026

  133. Croatia's passenger railway will charge battery trains at a station with its own solar and storage

    Croatia · 16 Jul 2026

  134. Google booked the first two phases of America's largest solar-plus-storage build - and the box is part of the deal

    United States · 15 Jul 2026

  135. An Istrian label printer put solar on its roof: 60 MWh in the first three months, EU-backed, no battery

    Croatia · 10 Jul 2026

  136. Croatia connected 218 MW of new solar in six months and still imported a third of its June power

    Croatia · 10 Jul 2026

  137. Croatia's regulator says the battery rulebook follows a new power law this autumn, with better terms from early 2027

    Croatia · 8 Jul 2026

  138. The US solar tax credit's start-building deadline has passed, and late projects now race a December 2027 finish line

    United States · 8 Jul 2026

  139. INA finished 11 MW of solar inside its Rijeka refinery, and the power is for a hydrogen machine

    Croatia · 2 Jul 2026

  140. Croatia opened its first household battery grant. The workplace lesson sits next door in the business call.

    Croatia · 30 Jun 2026

  141. Croatia finally priced the grid hook-up. Hybrid solar-plus-battery sites now pay on the higher of import or export.

    Croatia · 25 Jun 2026

  142. A Medulin tourism site is building 5 MWp of solar and a 5 MW / 10 MWh battery on an old clay pit

    Croatia · 29 May 2026

  143. Croatia's distributor named three ways to connect a battery. Co-located storage still may not charge from the grid.

    Croatia · 22 Jan 2026